Nineteen Step Bathroom
Renovation Process
1. Submit necessary permit paperwork to municipality.
2. Request certificate of insurance be sent to client, if requested by client.
3. Order cabinets, fixtures, and other items with long lead time.
4. Write job schedule allowing for lead times and inspection schedules.
5. Hold pre-construction meeting with client to review all aspects of construction process.
6. Secure dumpster for job debris removal.
7. Protect adjacent areas as needed.
8. Remove existing fixtures and finishes.
9. Relocate plumbing and electrical rough-ins as specified in contract.
10. Install insulation and drywall as specified.
11. Install bathroom cabinetry and millwork; template for counter tops.
12. Install, grout, and seal tile-work.
13. Template and install shower enclosure. 14. Paint all drywall and millwork.
15. Install plumbing fixtures, mirrors, medicine cabinets, towel bars and other bath accessories.
16. Final job cLearn-up and debris removal.
17. Remove any excess material, dumpster, and job sign.
18. Call for final inspection from township building department.
19. Enter job in company schedule for one year check-up.

 

 
Home | About Us | Product & Services | Getting Started | Featured Projects | Contact Us | Employment
Nuss Construction Company Inc.
119 Church Road, Marlton, NJ 08053 • Phone: (856) 988.9982 • Fax: (856) 988-9983
www.nussconstruction.com